O'Neil and Partners were engaged by Evolve Group Limited part way through the construction phase of this 2560 m² new build production facility to resolve disputes and to agree a final account with the Design and Build Contractor.
The successful resolution and agreement of the final account within the Client’s budget lead to O’Neil and Partners being appointed as Project Quantity Surveyors from inception on future phases of work to extend the facility.
Project Details
- Client: Evolve Group Limited
- Contract Sum: £1,100,000
- Main Contractor: Acorn Building Services Ltd
- Form Of Contract: JCT Design and Build
- Project Architect: PAB Chartered Architects Limited
- Consulting Engineer: Steve Hunt Partnership