This project comprised the general internal refurbishment of an existing dental practice, together with an extension to provide additional dental treatment rooms.
The works were carried out in a live environment with specific Health and Safety requirements to ensure the continuous operation of the clinic whilst the works were undertaken.
O’Neil and Partners provided full QS services, including initial feasibility budget cost estimating, traditional tendering procurement utilising measured Schedules of Works, preparation of contract documents, monthly interim valuations and cost reporting, and settlement and agreement of the final account.
Project Details
- Client: Manchester Primary Care Trust
- Contract Sum: £325,000
- Main Contractor: Projects Limited
- Project Architect: Taylor Young
- Services Engineer: Cameron Corporation
- Form of Contract: Intermediate Building Contract, 2005
Download Case Study
Download: Withington Dental Clinic - Case Study