This new build 1735 m² sixth form facility at Ripley St Thomas C of E High School provides modern state of the art classrooms and tutorial areas, a lecture / drama theatre, resource and study areas , IT suite, seminar room and students common room.
O’Neil and Partners acted as Project Quantity Surveyor, providing full services including initial feasibility budget cost estimating, preparation of contract documents, monthly interim valuations and cost reporting, and settlement and agreement of the final account.
Project Details
- Client: Ripley St Thomas Church of England High School
- Contract Sum: £2,400,000
- Main Contractor: Thomas Barnes and Sons
- Project Architect: Cowan & Co
- CDM Co-Ordinator: Cowan & Co
- Services Engineer: JRB Environmental Design Ltd
- Structural Engineer: Harrison & Taylor Ltd
- Form of Contract: JCT Intermediate Contract with Contractors Design
Download Case Study