Sidebar

Menu

Highfield Primary School

Under the Primary Capital Build Programme, Highfield Primary School received planning permission to provide additional classrooms, an outdoor learning zone and a new IT suite.

The scheme involved a new 2 storey extension housing a computer room, two classrooms and resource area, and an outdoor teaching area covered by a canopy.

Further extension and refurbishment of the existing school was also given planning permission, whilst the adjacent small library was demolished to provide a new car park and upgraded external play areas.

O’Neil & Partners are providing full QS services including initial feasibility budget cost estimating, traditional tendering procurement utilising measured Bills of Quantities, preparation of contract documents, monthly interim valuations and cost reporting, and settlement and agreement of the final account.

The project was completed on programme and within budget.

Project Details

  • Client: Highfield Primary School, Farnworth – The Borough Council of Bolton
  • Programme: 30 Weeks
  • Contract Sum: £1,262,882
  • Main Contractor: CityBuild (Manchester) Ltd
  • Project Architect: Good & Tillotson Ltd
  • Services Engineer: JJLC Engineering Design Services Ltd
  • Structural Engineer: Foxx Ltd
  • Form of Contract: JCT Intermediate Building Contract with Contractors Design 2011

Download Case Study

Download: Highfield Primary School - Case Study

Gallery

Highfield Primary School

Latest ONP News

Office & Retail

Hotels & Leisure

Sports Stadia

Health

Education

Refurbishment

Local Authority

Community

Industrial Developments

Residential

Icon made by SimpleIcon from www.flaticon.com is licensed under CC BY 3.0